Projects-1

Renovation and Installation backup system

Remove and reinstall existing electric infrastructure and installation of and electrical backup

Project Jurica
LocationPaseo Jurica
Panels:4x640W 2560Wstc
Inverter:SNRE EOV 8kW
BatterySNRE 10kWhr
GeneratorBriggs & Stratton 8kW
ATSHolaztec 3:[2:2]-►3phase
Netw.Phases 3
Voltage 240V

This project involved a complete renovation of the incoming electrical system, which included the installation of the ESS. The image below shows the “before” state.

Grid tied Solar

Installation of an on grid solar panel system

Project Jurica
Location:Jabimos
Panels:15x550W, 8250Wstc
Inverter:Huawei sun600
Battery non
Generatornon
ATSnon
Netw.Phases 3
Voltage 230V

Gas generator backup

Installation of a gas generator and transfer switch to back up a house

Project Jurica
Location:Robles
Panels:non
Inverter:non
Battery non
Generator Generac 6.5kW
ATS Holaztec 2:2:2Phase
Netw.Phases 2
Voltage 120/220V

Grid Tied Backup system

Backup system to provide electricity for a pump during raining season

Project Jurica
Location:Cedros
Panels:non
Inverter:SNRE EOH 8kW
Battery SNRE 10kWhr
Generator non
ATSnon
Netw.Phases 3
Voltage 240V

Grid tied Solar and backup

Installation of a bidirectional hybrid solar panel and backup system

Project Mexico City
Location:Santa Fe
Panels:non
Inverter:Huawei Sun2000
Battery Luna 5kW
Generator non
ATSHuawei Backup Box-B1
Netw.Phases 3
Voltage 240V

Grid tied Solar and backup

Installation of a bidirectional hybrid solar panel and backup system

Project Maravatio
LocationMelchor Ocampo
Panels:4x640W 2560Wstc
Inverter:SNRE EOV 5kW
BatterySNRE 5kWhr
Generator non
ATSHolaztec 3:1-►3phase
Netw.Phases 3
Voltage 240V

Grid tied Solar

Installation of a solar panels to compensate the cost of the electricity bill

Project Sonterra
LocationSonterra-3
Panels:Bifacial 2x760W 1400Wstc
Inverter:Hoymiles HMS2000T4
Battery
Generator
ATS
Netw.Phases 2
Voltage 120/240V



Comments are closed.